Evidence atlas
The record between announcement and capacity.
Rotating Data traces the power, land, operators, equipment, approvals, capital, and time that stand between an AI infrastructure claim and energized capacity.
Project dossier
Childress AI campus
Crusoe × Lancium · primary-source record
Swipe to follow all seven dependencies
- PowerSource-backed
- LandSource-backed
- OperatorResolved
- EquipmentOpen
- ApprovalsOpen
- CapitalUndisclosed
- ScheduleTarget
Dependency notes
- 01Power1.0 GW grid-connected scaleSource-backed
Disclosed campus scale. Deliverability still depends on phased interconnection and equipment.
- 02Land270-acre Childress siteSource-backed
The issuer record identifies the site footprint in Childress, Texas.
- 03OperatorCrusoe + LanciumResolved
Lancium controls the site and energy layer. Crusoe designs, builds, and operates the campus.
- 04EquipmentElectrical scopeOpen
Transformer, switchgear, and delivery milestones are not resolved in the current public record.
- 05ApprovalsPermitting pathOpen
The current record does not yet resolve the complete permitting and approval sequence.
- 06CapitalProject financingUndisclosed
Project value, customer identity, and commercial financing terms remain undisclosed.
- 07ScheduleQ3 2026 constructionTarget
A stated construction target—not delivered or energized capacity.
The parties, site, disclosed scale, and construction target are sourced. Equipment milestones, financing, customer identity, and phased energization remain unresolved. Read the complete evidence record
Evidence ledger
What entered the record.
New commitments are dated, graded, and left open where the source is silent.
All 309 recordsNscale + Third Point + NVIDIA + other note investors
$3.36B convertible loan notes: $2.36B tranche at closing plus $1B NVIDIA commitment expected mid-November 2026
Akamai Technologies + Anthropic
$11.6B contractual commitment over seven years; additional $9B is a potential expansion, not the announced commitment
Generac Holdings + Amazon
Expected $2.4B of initial deliveries in 2027–2028; warrant vesting tied to up to $8B of generator payments
Google + Finnish infrastructure and energy partners
At least €13B planned investment in 2027–2028 across four Finnish locations
A disclosed claim is not a resolved dependency, and a target is not delivered capacity.