Confirms Applied Digital’s North Dakota platform is no longer just a CoreWeave story: a second major hyperscaler is reserving AI-factory scale capacity with an option on the full 1 GW campus.
Source-supported terms
What was disclosed
- 01
Applied Digital announced an approximately 15-year lease for 200 MW of critical IT load at Polaris Forge 2.
- 02
The lease represents about $5B of contracted revenue.
- 03
The hyperscaler holds a right of first refusal for an additional 800 MW, matching the 1 GW campus expansion potential.
- 04
The initial 200 MW are expected to phase online during 2026 and 2027.
Disclosure boundary
What is known—and what is not
Signed lease announced publicly; customer identity, detailed pricing, power contract and full lease terms are not public.