Home/Deal Room/Google advances Texas and Minnesota data-center buildouts

Data centers · Evidence brief

Google advances Texas and Minnesota data-center buildouts

Google + AES + Xcel Energy + Form Energy

Primary sourcePress release only2026-02-24
Deal structureData-center development / utility energy agreements / co-located generation
GeographyWilbarger County, Texas + Pine Island, Minnesota
Infrastructure layersData centers + power + storage + utility tariffs
Disclosed scaleNew Google data centers in Wilbarger County, Texas and Pine Island, Minnesota; Minnesota energy package includes 1.4 GW wind, 200 MW solar and 300 MW iron-air battery storage

Why it matters

The strategic read

Shows Google turning data-center expansion into a power-structure problem: co-located generation and air cooling in Texas, plus a Minnesota utility tariff package with wind, solar, long-duration storage and customer-funded grid capacity. The AI buildout bottleneck is shifting from abstract capex to permitted land, interconnection, power contracts, cooling and ratepayer politics.

Source-supported terms

What was disclosed

  1. 01

    Google announced a new data center in Wilbarger County, Texas that will be co-located with clean power developed by AES.

  2. 02

    AES said the Texas site was ready for construction with land, interconnection agreements and co-located generation under 20-year PPAs.

  3. 03

    Google said the Wilbarger County facility will use advanced air-cooling to eliminate operational water use beyond critical campus operations.

  4. 04

    Google also announced Pine Island, Minnesota as the future home of its first Minnesota data center in partnership with Xcel Energy.

  5. 05

    The Minnesota package includes 1,400 MW of wind, 200 MW of solar and 300 MW of Form Energy iron-air battery storage under the Clean Energy Accelerator Charge structure.

  6. 06

    Google said it will pay the costs associated with its electric service and provide $50M for Xcel capacity and resilience programs.

Disclosure boundary

What is known—and what is not

Primary Google announcements and CRN market reporting; full utility agreements, PPAs, site schedules, interconnection documents, construction contracts and customer workload allocation are not public.