Joule launches BetterGrid 1+ GW Utah AI campus platform

Joule BetterGrid + Clear Lake Investments + Foulger Pratt + Caterpillar

Primary sourcePress release only2026-02-05
Deal structureAI data-center platform launch / behind-the-meter power and campus development
GeographyMillard County / Delta-area Utah high desert
Infrastructure layersData centers + power + cooling + financing
Disclosed scale$60M Series B-backed platform; 4,000-acre entitled Millard County campus; 1+ GW Phase I and 1.7 GW of Caterpillar generation equipment secured

Why it matters

The strategic read

Adds the second Millard County behind-the-meter AI campus to the map. Joule is not framed around a named hyperscaler lease yet; the signal is entitled land, water rights, gas interconnects and generator supply being packaged as speed-to-power infrastructure for AI workloads.

Source-supported terms

What was disclosed

  1. 01

    Joule announced the BetterGrid platform for high-density AI workloads from its fully entitled Millard County, Utah data-center campus.

  2. 02

    The company said it closed $60M in Series B financing led by Clear Lake Investments and Foulger Pratt after a $3M Series A in 2025.

  3. 03

    Joule said it has secured 1.7 GW of Caterpillar power-generation equipment, with first delivery scheduled for March.

  4. 04

    The company says it controls 4,000 acres of entitled land, 10,000 acre-feet of senior water rights and direct natural-gas interconnections.

  5. 05

    The campus page describes a 1+ GW Phase I, six facilities, liquid-cooling readiness, fiber from Lumen, Zayo, AT&T and Verizon, and Q4 2027 RFS milestones.

  6. 06

    Joule says its behind-the-meter power platform is designed to avoid multi-year grid interconnection delays.

Disclosure boundary

What is known—and what is not

Primary company launch announcement and campus page; named hyperscaler tenant, lease value, final power plant permits, EPC contracts, equipment delivery proof, customer reservation terms, full financing documents and construction schedule are not public.