Why it matters
The strategic read
Turns Meta’s West Texas site from a large campus into a gigawatt-class AI infrastructure node. The disclosure is unusually explicit about the gating resources: closed-loop liquid cooling, El Paso Electric planning, full-cost energy treatment, clean-energy additions to the Texas grid, and water-restoration commitments alongside the data-center expansion.
Source-supported terms
What was disclosed
- 01
Meta updated its El Paso AI-focused data-center announcement on March 26, 2026 to say the site will officially grow to 1 GW.
- 02
The company increased the initial $1.5B investment to more than $10B.
- 03
Meta expects to support more than 300 operational jobs after completion and more than 4,000 construction workers at peak.
- 04
The campus is designed for AI workloads and future AI-enabled hardware, with systems flexible enough for traditional servers and future AI configurations.
- 05
Meta plans to use a water-efficient closed-loop system that recirculates water and uses no operational water for a majority of the year.
- 06
Meta said it continues to work with El Paso Electric and energy developers and has projects under contract adding more than 5,000 MW of clean energy to the Texas grid.
- 07
Meta Data Centers said general-contractor construction opportunities are tied to JE Dunn and Hensel Phelps.
Disclosure boundary
What is known—and what is not
Primary Meta announcement and Meta Data Centers local update; full construction packages, utility service agreements, power purchase details, load ramp, equipment mix, network design and site phasing are not fully public.