Why it matters
The strategic read
Adds a gigawatt-scale long-duration storage lane to Meta’s AI power stack. The deal moves beyond conventional renewable PPAs by reserving multi-day energy storage capacity meant to firm clean generation for data centers, with a small first project that can unlock a much larger supply contract.
Source-supported terms
What was disclosed
- 01
Noon Energy announced an agreement with Meta to reserve up to 1 GW / 100 GWh of ultra-long-duration energy storage capacity.
- 02
The deployment begins with a 25 MW / 2.5 GWh project scheduled for completion by 2028.
- 03
After successful completion of the initial project, Noon says it will begin delivering systems under a 1 GW / 100 GWh supply contract.
- 04
Noon describes the systems as modular reversible solid-oxide fuel-cell storage designed for 100+ hour discharge duration.
- 05
Meta said the agreement is intended to accelerate reliable energy deployment for data centers and improve grid resilience and firm power availability.
Disclosure boundary
What is known—and what is not
Primary company announcement; full reservation agreement, supply-contract mechanics, project location, pricing, Meta facility matching, interconnection terms, production-capacity milestones, and termination rights are not public.