Why it matters
The strategic read
Shows hyperscale AI/data-center growth pulling firm clean power and storage into utility planning. Amazon is tying planned Reno-area data-center operations to a portfolio that mixes around-the-clock geothermal with solar-plus-storage capacity rather than relying on generic renewable credits.
Source-supported terms
What was disclosed
- 01
Amazon is backing 700 MW of new carbon-free generation and storage in Nevada to support future data-center operations in the Reno area.
- 02
Zanskar announced a 20-year PPA with NV Energy to deliver 100 MW of geothermal power by 2030, subject to approval of NV Energy’s 2026 Integrated Resource Plan by the Public Utilities Commission of Nevada.
- 03
The geothermal agreement runs through 2050 and covers multiple projects that Zanskar expects to construct, own, and operate as a portfolio.
- 04
The broader Amazon/Nevada package also includes 600 MW of solar paired with 600 MW of battery storage from Primergy to support capacity needs and grid flexibility.
Disclosure boundary
What is known—and what is not
Public announcement / reporting layer; utility IRP approval is still required and full PPA, pricing, site, and interconnection terms are not public.