Why it matters
The strategic read
Adds Latin America to the current wave of AI-specific, high-density data-center buildouts. Ascenty says the new contracted capacity equals more than 40 percent of everything it built over its first 15 years, with direct-to-chip liquid cooling, up to 1 MW per rack, dedicated transmission infrastructure and global customer demand pulling Brazil into the AI factory map.
Source-supported terms
What was disclosed
- 01
Ascenty announced a $1.2B investment plan, about 5.9B reais, to deliver new AI-oriented data-center capacity in Brazil over the next 18 months.
- 02
The program covers 150 MW of contracted capacity, which Ascenty said represents more than 40 percent of the capacity it installed over its first 15 years of operation.
- 03
CEO Chris Torto said Ascenty closed contracts in three months representing 40 percent of everything the company had done in 15 years.
- 04
Sumaré 3 is planned as Ascenty's first Latin America facility designed from the ground up for large-scale AI workloads.
- 05
Sumaré 3 is expected to start with 90 MW of capacity, with potential for another 90 MW of expansion, across 48,000 square meters.
- 06
Construction of Sumaré 3 began in March 2026, with delivery scheduled for the third quarter of 2027.
- 07
The Sumaré 3 design includes direct-to-chip liquid cooling, closed-loop cooling and densities up to 1 MW per rack.
- 08
At Vinhedo, Ascenty is expanding Vinhedo 2 from 50 MW to 80 MW and adding Vinhedo 3 with 90 MW dedicated to AI workloads, while also developing Vinhedo 4 and Vinhedo 5.
- 09
Ascenty also announced a sixth São Paulo data center, adding 20 MW for hyperscale and corporate clients.
- 10
For Sumaré 3, Ascenty built a 32 km transmission line from a CPFL substation in Santa Bárbara d'Oeste to the Sumaré campus and secured grid access through Brazil's ONS.
- 11
Ascenty operates or is building 40 data centers across Brazil, Chile, Mexico and Colombia, connected by its own roughly 4,000 km fiber network.
- 12
Ascenty is a joint venture between Digital Realty and Brookfield Infrastructure.
Disclosure boundary
What is known—and what is not
Near-primary DCD report based on Ascenty press briefing and company executive comments; full customer contracts, tenant identities, site-by-site lease terms, capex draw schedule, financing split between owners, utility agreements, equipment suppliers and EPC awards are not fully public.