Why it matters
The strategic read
Adds another crypto-to-AI conversion pathway at gigawatt scale. Core Scientific is using acquisitions, grid expansion, behind-the-meter generation planning and adjacent land control to turn Muskogee from a single leased GB300-ready building into a 1 GW leasable high-density compute campus.
Source-supported terms
What was disclosed
- 01
Core Scientific announced a multi-tiered strategy to scale its Muskogee, Oklahoma campus to approximately 1.5 GW of gross power, or approximately 1.0 GW of leasable power.
- 02
Core Scientific completed the Polaris DS acquisition on August 13, 2026 for approximately $444M in cash, subject to customary post-closing adjustments.
- 03
The acquisition secured approximately 440 MW of currently in-service gross, grid-connected power capacity under existing electric service agreements with Oklahoma Gas & Electric.
- 04
The original 8-K described about 40 acres adjacent to Core Scientific’s existing Muskogee data-center operations, an electrical substation, the electric service agreements and related utility contracts among Polaris's material assets.
- 05
Core Scientific remains on track to deliver the next approximately 82 MW at Muskogee to its customer beginning in the second half of 2027.
- 06
Core Scientific said its current leased 70 MW Muskogee building designed to support the NVIDIA GB300 platform is in final testing and commissioning, with second-quarter 2026 delivery to its customer on track.
- 07
Core Scientific also has load studies underway for grid-connected expansion and has developed a scalable behind-the-meter solution plan supported by approximately 250 acres of secured land.
Disclosure boundary
What is known—and what is not
The acquisition closed on August 13, 2026 for approximately $444M in cash and secured about 440 MW of in-service grid-connected power under existing OG&E agreements. The full purchase agreement, post-closing adjustments, future customer leases, full power-delivery milestones, grid-expansion study results, behind-the-meter generation plan, construction contracts, financing links and operating economics are not public in full.