Home/Deal Room/Enbridge and Meta expand Cowboy solar-plus-storage power lane

Power · Evidence brief

Enbridge and Meta expand Cowboy solar-plus-storage power lane

Enbridge + Meta Platforms + Cheyenne Light, Fuel and Power

Primary sourcePress release only2026-05-19
Deal structureSolar-plus-storage project / data-center power procurement
GeographyCheyenne, Wyoming / Meta data-center operations
Infrastructure layersPower + data centers + grid storage
Disclosed scaleUS$1.2B expected Enbridge construction investment; 365 MW solar plus 200 MW / 1,600 MWh battery storage; Enbridge-Meta contracted capacity now totals about 1.6 GW across North America

Why it matters

The strategic read

Shows Meta adding dispatchable renewable power close to data-center load, not just generic renewable-credit matching. The Cowboy Project pairs a large solar build with a long-duration battery system under a utility large-load tariff, giving Meta another named power lane as its AI data-center footprint expands.

Source-supported terms

What was disclosed

  1. 01

    Enbridge announced the first phase of the Cowboy Project near Cheyenne, Wyoming, to support Meta data-center operations.

  2. 02

    The project combines 365 MW of solar generation with a 200 MW / 1,600 MWh battery energy storage system.

  3. 03

    Enbridge says the Cowboy Project expands its Meta partnership to approximately 1.6 GW of contracted capacity across North America.

  4. 04

    The broader Enbridge-Meta portfolio includes Clear Fork Solar at 600 MW, Easter Wind at 152 MW, and Cone Wind at 300 MW in Texas.

  5. 05

    Enbridge expects to invest approximately US$1.2B to construct the Cowboy solar facility and BESS.

  6. 06

    The project is expected to enter service by the end of 2027.

  7. 07

    Cheyenne Light, Fuel and Power will use its Large Power Contract Service tariff to serve the large-load customer while providing ratepayer protections.

Disclosure boundary

What is known—and what is not

Primary company announcement; PPA/tolling prices, full utility tariff implementation, battery dispatch terms, data-center load allocation, interconnection details, financing documents, and EPC contracts are not public.