RangeIDC-backed EGSB plans $5B Batam AI data center

Range Intelligent Computing Technology (RangeIDC) + PT Equator Gate System Batam + BP Batam + PT PLN Batam

Near-primary sourcePress release only2026-05-25
Deal structureAI data-center campus investment / power-purchase agreement
GeographyNongsa, Batam, Riau Islands, Indonesia
Infrastructure layersData centers + power infrastructure + construction / EPC + cloud capacity + networking
Disclosed scaleUS$5B / about Rp88T investment for a high-density AI data-center project on a 30-hectare site in Nongsa, Batam, backed by China-based RangeIDC, with a PT PLN Batam power-purchase agreement signed to supply the facility

Why it matters

The strategic read

Adds a third major Indonesia AI-infrastructure power lane beside BDx and Digital Edge. Batam is positioning itself as a Singapore-adjacent execution hub for high-density AI capacity, and RangeIDC is using the island for its first international expansion. The receipt ties Chinese data-center capital, BP Batam fast-track permitting, PLN power supply, local workforce development and regional cloud / semiconductor ecosystem ambitions into one Southeast Asia buildout.

Source-supported terms

What was disclosed

  1. 01

    Antara reported on May 25, 2026 that BP Batam is overseeing a US$5B / about Rp88T artificial-intelligence data-center investment in Batam, Riau Islands.

  2. 02

    The project is planned for a 30-hectare site in Nongsa, Batam.

  3. 03

    The developer is PT Equator Gate System Batam, an Indonesian AI data-center developer backed by China-based Range Intelligent Computing Technology Company Limited, also known as RangeIDC.

  4. 04

    Bernama reported the same May 25 project details and said RangeIDC selected Batam as its first international expansion location outside China for a high-density AI data center.

  5. 05

    BP Batam said PT PLN Batam signed an electric power-purchase agreement with PT Equator Gate System Batam to support stable and sustainable power supply for the data center.

  6. 06

    BP Batam said the first agreement reflects Batam's readiness to support global-standard hyperscale AI data-center investment.

  7. 07

    BP Batam Deputy for Investment Fary Djemy Francis said the authority would support the project through a fast-track execution mechanism to accelerate realization.

  8. 08

    Antara reported on May 28, 2026 that Indonesia's Ministry of Transmigration is preparing workforce support for the same Rp88T AI data-center investment.

  9. 09

    W.Media recirculated the project on June 11, 2026, noting the PLN Batam / EGSB power-purchase agreement and RangeIDC's first international expansion.

  10. 10

    Officials said the project is expected to attract cloud-computing, semiconductor-ecosystem and AI-services industries and create about 700 to 800 professional jobs.

Disclosure boundary

What is known—and what is not

Near-primary Indonesian state-news / regional wire reporting based on BP Batam statements, plus W.Media recirculation. Public details disclose the investment amount, RangeIDC/EGSB backing, Batam/Nongsa location, 30-hectare site, PLN Batam power-purchase agreement and BP Batam fast-track support. Public materials do not disclose MW/MVA capacity, PPA term, power price, load-ramp schedule, grid-upgrade cost allocation, land-control documents, construction start date, EPC contractor, cooling design, fiber providers, tenant/customer commitments, financing structure or delivery milestones.