Home/Deal Room/Stratos clears local path for 9 GW Utah AI campus

Data centers · Evidence brief

Stratos clears local path for 9 GW Utah AI campus

Stratos + O’Leary Digital + MIDA + Box Elder County

Primary sourcePermit / utility filing2026-05-04
Deal structureProject-area approval / hyperscale AI data-center and on-site power campus
GeographyHansel Valley / western Box Elder County, Utah
Infrastructure layersData centers + power infrastructure + policy / permitting
Disclosed scaleRoughly 40,000-acre Box Elder County project area; Phase One has 3 GW committed and the full buildout is projected around 9 GW with on-site generation and long-term county revenue participation

Why it matters

The strategic read

Adds the most politically visible Utah AI megacampus to the archive. The core signal is not a named hyperscaler lease yet; it is state and county machinery clearing a 40,000-acre, on-site-power AI campus that could dwarf normal data-center interconnection requests and turn MIDA into a major AI-infrastructure land-use vehicle.

Source-supported terms

What was disclosed

  1. 01

    MIDA describes the Stratos Project Area as a major energy and technology infrastructure initiative in western Box Elder County approved by the MIDA Board and the Box Elder County Commission.

  2. 02

    The project area is located on approximately 40,000 acres in unincorporated Box Elder County and is planned in phases with environmental review, infrastructure coordination and community engagement.

  3. 03

    MIDA says Stratos is intended to support artificial intelligence, cloud computing and mission-critical defense operations with dedicated on-site power generation.

  4. 04

    MIDA states that Phase One has a committed 3 GW and is projected to generate about $30M annually, with a roughly 9 GW buildout projected to generate about $108M annually.

  5. 05

    Box Elder County’s public fact sheet says the project will produce all power it needs on site using natural gas from the nearby Ruby Pipeline.

  6. 06

    The county fact sheet says Stratos would use on-site non-potable water and closed-loop cooling, while opponents have raised water, governance, heat and local-control concerns.

Disclosure boundary

What is known—and what is not

Archive catch-up based on MIDA and Box Elder County public materials; named tenant commitments, final generation assets, environmental approvals, water-use permits, lease/customer contracts, financing structure, EPC awards and construction schedule are not fully public.