TeraWulf acquires 1+ GW Muskie HPC campus in Kentucky

TeraWulf + Industrial Equity Partners + Kentucky Power / AEP

Primary sourceSEC summary2026-05-26
Deal structureAI / HPC data-center campus acquisition and power-delivery framework
GeographyEastern Kentucky / EastPark Industrial Park
Infrastructure layersData centers + power infrastructure + utility interconnection
Disclosed scaleMore than 1 GW planned data-center capacity; initial 500 MW targeted to ramp in 2H 2028 and another 500 MW targeted for 2H 2030; 285 acres within EastPark Industrial Park

Why it matters

The strategic read

Adds another public miner-to-AI infrastructure expansion where the scarce asset is not GPUs but controllable land, transmission access and utility-scale power delivery. TeraWulf is turning Kentucky into a second major campus market beside Lake Mariner and Justified Data, with Kentucky Power building a 345 kV substation tied into a 765 kV network.

Source-supported terms

What was disclosed

  1. 01

    TeraWulf announced the acquisition of the Muskie Data Campus from Industrial Equity Partners.

  2. 02

    The site is expected to support more than 1 GW of AI and HPC data-center capacity over time.

  3. 03

    Delivery of the initial 500 MW is expected to ramp beginning in the second half of 2028, with another 500 MW targeted for the second half of 2030.

  4. 04

    The campus includes about 285 acres of owned and controlled land within the 1,000-acre EastPark Industrial Park, with optional adjacent acreage for future expansion.

  5. 05

    Kentucky Power, an AEP company, is constructing a 345 kV substation connected to the existing 765 kV transmission network.

  6. 06

    Transmission infrastructure and energy service agreements were executed concurrently with the acquisition under the applicable Industrial General Service tariff for large loads.

  7. 07

    TeraWulf said the site is already zoned for the intended use, permitting is underway, and limited site work is required to support data-center construction.

Disclosure boundary

What is known—and what is not

Primary announcement and 8-K summary are public; purchase price, MIPA terms, power-delivery pricing, customer commitments, final construction phasing, capex budget, financing plan and permitting milestones are not fully public.