Adds a European power-procurement receipt to Amazon's AI-era cloud buildout. The PPA covers roughly 61 percent of Gennaker, gives Skyborn revenue certainty for a near-gigawatt offshore-wind project, and ties hyperscaler power demand to a German market record at the same time AWS is expanding around Frankfurt and Hesse. It is a clean example of the Deal Room pattern where data-center growth shows up first as grid-scale renewable offtake before the server halls are named.
Source-supported terms
What was disclosed
- 01
Amazon and Skyborn Renewables announced on June 19, 2026 that they signed a 600 MW Power Purchase Agreement for carbon-free electricity from the Gennaker offshore wind farm in the German Baltic Sea.
- 02
Skyborn said the agreement is the largest single PPA ever signed in Germany and one of the largest in Europe.
- 03
Amazon's long-term commitment to buy Gennaker power gives Skyborn financial certainty to move forward with construction.
- 04
Gennaker is planned to add up to 976.5 MW of new offshore-wind capacity to Germany's electricity system.
- 05
The project is located about 15 kilometres north of the Fischland-Darss-Zingst peninsula in Mecklenburg-Western Pomerania.
- 06
Skyborn secured the construction permit for Gennaker in December 2025.
- 07
The project is expected to feature 63 offshore wind turbines rated at 15 MW each.
- 08
Construction is expected to begin after Skyborn reaches financial close in summer 2026, with operations expected toward the end of 2028.
- 09
Skyborn said Gennaker represents a major EUR3B investment in Mecklenburg-Western Pomerania and that EEW Special Pipe Constructions will manufacture monopile foundations in Rostock.
- 10
Skyborn said Amazon's German carbon-free energy portfolio now includes 12 projects with more than 1.3 GW of total capacity.
- 11
DCD reported the PPA as Amazon's largest in Germany and noted AWS's Frankfurt cloud-region operations plus data-center developments outside Frankfurt in Schoneck and Maintal.
Disclosure boundary
What is known—and what is not
Primary Skyborn / Amazon announcement plus DCD near-primary coverage. Public materials disclose the buyer, seller, 600 MW contracted capacity, Gennaker project size, construction-permit status, expected financial-close and operations timing, turbine count, EUR3B investment framing, regional supply-chain participation and Amazon Germany portfolio context. Public materials do not disclose the full PPA, price, tenor, delivery profile, contract-for-difference structure if any, balancing terms, curtailment risk allocation, cancellation rights, Skyborn financing package, grid-connection terms, final FID documents, Amazon workload allocation, data-center energy-matching methodology or whether the electricity is tied to specific AWS facilities.