Home/Deal Room/EdgeConneX files $1.4B Bastrop data-center expansion

Data centers · Evidence brief

EdgeConneX files $1.4B Bastrop data-center expansion

EdgeConneX + Burr Computer Environment + Gensler + Texas TDLR

Primary sourcePermit / utility filing2026-06-03
Deal structureData-center construction filings / Austin-area hyperscale campus expansion
GeographyCedar Creek / Bastrop County, Texas, near Austin
Infrastructure layersData centers + power infrastructure + construction / EPC + cloud capacity
Disclosed scaleTwo privately funded 730,000-square-foot data-center buildings in Cedar Creek / Bastrop County, Texas, each filed at an estimated $700M construction cost, for a combined $1.4B project value and targeted construction from June 2026 through December 2028

Why it matters

The strategic read

Adds another Central Texas hyperscale construction receipt to the AI-infrastructure map. EdgeConneX already frames the Austin/Bastrop campus as 240 MW across AUS02-04, and the new EDCAUS11/EDCAUS12 filings show two more very large buildings moving from land-control rumor into state-registered construction projects with named designer, owner entity, dates, square footage and private capital commitment.

Source-supported terms

What was disclosed

  1. 01

    Texas Department of Licensing and Regulation project TABS2026021187 registered EDCAUS11 on May 26, 2026 at 6682 FM 535 in Cedar Creek, Bastrop County, Texas.

  2. 02

    The EDCAUS11 filing lists new construction of a 729,537-square-foot, one-story data center with supporting office space and associated site improvements.

  3. 03

    TDLR lists the EDCAUS11 estimated cost at $700M, with work starting June 30, 2026 and completing December 31, 2028.

  4. 04

    Texas TDLR project TABS2026021191 registered EDCAUS12 at the same address, also with a 729,537-square-foot, one-story data-center scope.

  5. 05

    TDLR lists the EDCAUS12 estimated cost at $700M, with the same June 30, 2026 start date and December 31, 2028 completion target.

  6. 06

    Both filings say the projects are privately funded, on private land, for private use, with tenant not assigned in the public TDLR records.

  7. 07

    Both filings list Burr Computer Environment Inc. as owner and Gensler Architecture, Design & Planning, P.C. as design firm.

  8. 08

    DCD reported that EdgeConneX filed to build the two 730,000-square-foot facilities, dubbed EDCAUS11 and EDCAUS12, on a 180-acre parcel at 6682 FM 535 that EdgeConneX acquired in November 2025.

  9. 09

    DCD tied the site to EdgeConneX AUS02, one of the company's in-development Austin-area data centers, and noted EdgeConneX's public Austin page describes the combined AUS02-04 sites as 240 MW.

Disclosure boundary

What is known—and what is not

Primary Texas TDLR permit / architectural-barriers filings for EDCAUS11 and EDCAUS12, plus DCD near-primary reporting that attributes the projects to EdgeConneX and links them to the Austin/Bastrop campus. Public records disclose estimated cost, address, owner entity, designer, square footage, private funding status and construction dates. Tenant/customer, exact IT load by building, utility-service agreements, interconnection upgrades, power price, tax-abatement terms, EPC contractor, cooling design, network providers and final campus phasing are not fully public.