Home/Deal Room/Firmus secures 600 MW South Australia AI factory power

Power · Evidence brief

Firmus secures 600 MW South Australia AI factory power

Firmus Technologies + Gunvor Group + GreenPoint Energy

Primary sourcePress release only2026-06-30
Deal structure12-year wholesale energy supply agreement / AI factory power and storage offtake
GeographyTailem Bend, Stirling North and Brinkworth / South Australia
Infrastructure layersPower infrastructure + data centers + cloud capacity + cooling
Disclosed scale12-year agreement for 600 MW of firm electricity supporting Firmus Project Southgate AI Factory campuses in South Australia; Gunvor will support 1.2 GW of new renewable generation and 1.5 GWh of new battery storage by 2032, including long-term offtake tied to GreenPoint Energy's 200 MW / 800 MWh Koolunga BESS, while Firmus describes the Tailem Bend and Stirling North first-phase campuses as representing 2.7 GW of planned capacity

Why it matters

The strategic read

Turns Firmus' Australia AI factory plan into a grid-facing power receipt. The scarce input is not only data-center land or GPU ambition: Firmus is locking a 12-year firm-electricity supply model with demand response, renewable generation, battery storage and dry-mode cooling commitments around multi-gigawatt planned AI-factory campuses in South Australia. It also adds Gunvor and GreenPoint to the AI-infrastructure supply chain as energy trading and storage counterparties.

Source-supported terms

What was disclosed

  1. 01

    Firmus announced a 12-year wholesale energy supply agreement with Gunvor Group for 600 MW of firm electricity.

  2. 02

    The agreement supports the next phase of Project Southgate, Firmus' strategy to develop large-scale AI Factory campuses across regional Australia.

  3. 03

    Firmus said Gunvor will support development of 1.2 GW of new renewable generation and 1.5 GWh of new battery storage by 2032 for Firmus' South Australian expansion.

  4. 04

    The agreement underpins the first phase of Firmus' South Australian AI Factory campuses at Tailem Bend and Stirling North, which Firmus says represent 2.7 GW of planned capacity.

  5. 05

    The deal includes demand response: Firmus will reduce electricity consumption for up to 220 hours each year when wholesale prices exceed agreed thresholds.

  6. 06

    Firmus said the agreement includes long-term offtake supporting GreenPoint Energy's Koolunga Battery Energy Storage System near Brinkworth.

  7. 07

    Koolunga is described as a 200 MW / 800 MWh grid-forming battery that will represent more than half of Firmus' initial firming capacity commitment.

  8. 08

    Firmus also launched Australian Energy and Water Stewardship policies covering renewable procurement, battery storage, demand response, network costs, cooling technology and transparent reporting.

  9. 09

    The water policy says Firmus will prioritize dry-mode cooling, site-specific water planning and recycled or non-potable water where practical.

  10. 10

    Firmus says it will fund its own project-specific transmission connection infrastructure and purchase electricity on commercial terms without seeking preferential tariffs or subsidies.

  11. 11

    Gunvor's APAC power trading and origination head said the transaction shows how long-term customer demand can unlock renewable supply, firming and risk management through one commercial solution.

Disclosure boundary

What is known—and what is not

Primary Firmus announcement, supported by Firmus' same-day energy and water policy release and W.Media / Google News pickup. Public materials disclose the named parties, 12-year wholesale supply agreement, 600 MW firm-electricity figure, 1.2 GW renewable-generation support, 1.5 GWh battery-storage support, GreenPoint Koolunga 200 MW / 800 MWh BESS offtake, demand-response hours, Tailem Bend / Stirling North campus framing and 2.7 GW planned-capacity statement. Public materials do not disclose the full energy supply contract, price, capacity factors, exact renewable projects, interconnection queue status, full transmission connection documents, project financing, customer/offtake names, construction / EPC awards, GPU procurement, final campus phasing, permits, delivery remedies or whether the full 2.7 GW planned capacity is binding today.