Oracle signs $67B of AI infrastructure contracts in Q4

Oracle + large AI cloud infrastructure customers including OpenAI-linked campus demand

Primary sourceSEC summary2026-06-10
Deal structureAI cloud infrastructure contracts / prepaid and customer-supplied GPU capacity commitments
GeographyOracle Cloud Infrastructure AI datacenter portfolio including Abilene and Shackelford County, Texas; Dona Ana County, New Mexico; Saline County, Michigan; and Port Washington, Wisconsin
Infrastructure layersCloud capacity + data centers + chips / compute + power infrastructure + networking
Disclosed scale$67B of AI infrastructure contracts signed in Oracle Q4 FY2026, with the prepaid and customer-supplied hardware portions of Oracle large AI contracts totaling $75B; Oracle reported $638B of remaining performance obligations, 1.2 GW brought online in FY2026, another 1 GW expected in Q1 FY2027, and multiple OpenAI-leased campuses in delivery

Why it matters

The strategic read

Turns Oracle from a single Stargate/Abilene landlord into one of the clearest public ledgers for contracted frontier-AI cloud capacity. The Q4 disclosure shows customers prepaying or supplying GPUs at massive scale, reducing Oracle funding needs while pushing datacenter, power, networking and fuel-cell-backed clean-energy buildout. It also puts concrete delivery markers around the OpenAI campus network: Abilene capacity is already partly delivered, 115 MW is online at Shackelford ahead of schedule, and additional New Mexico, Michigan and Wisconsin campuses have customer-delivery windows.

Source-supported terms

What was disclosed

  1. 01

    Oracle announced Q4 FY2026 results on June 10, 2026, with remaining performance obligations ending the quarter at $638B, up $85B sequentially and 363% year over year.

  2. 02

    Oracle said most of the RPO increase in Q3 and Q4 came from large-scale AI contracts where customers prepaid Oracle for GPUs or bought and supplied GPUs to Oracle.

  3. 03

    Oracle disclosed that prepaid and customer-supplied hardware portions of its large AI contracts now total $75B.

  4. 04

    DCD reported on June 11, 2026 that Oracle signed $67B in AI infrastructure contracts in Q4, with the majority either bring-your-own hardware or prepaid.

  5. 05

    Oracle said it raised $43B of debt financing and $5B of equity financing in FY2026, and expects to raise about $40B through debt and equity financing in FY2027, including its previously announced $20B at-the-market equity issuance.

  6. 06

    Oracle said its capital investment program supports unprecedented AI Cloud Infrastructure opportunities.

  7. 07

    Oracle tied the RPO and revenue increases to demand for cloud infrastructure for AI training and inference.

  8. 08

    Oracle said it is building datacenters intended to use clean energy from natural-gas fuel cells to generate electricity with minimal emissions.

  9. 09

    DCD reported that Oracle brought 1.2 GW online during FY2026 and expects another 1 GW in Q1 FY2027.

  10. 10

    DCD quoted Oracle management saying Abilene, Texas has delivered 42 percent of total capacity, with another 35 percent expected in the next 90 days and the remainder in the subsequent quarter.

  11. 11

    DCD reported that 115 MW of power capacity is already online at the Shackelford, Texas site ahead of schedule, with customer delivery beginning in the first half of calendar 2027.

  12. 12

    DCD reported that customer delivery is expected in the first half of calendar 2027 for Dona Ana County, New Mexico, the second half of 2027 for Saline County, Michigan and Port Washington, Wisconsin, and that the five campuses are set to be leased to OpenAI.

Disclosure boundary

What is known—and what is not

Primary Oracle Q4 FY2026 release plus DCD earnings-call coverage. Public details disclose aggregate RPO, prepaid/customer-supplied GPU hardware exposure, Q4 AI infrastructure contract value, funding plan, high-level energy approach, gigawatt-scale delivery pace, and named OpenAI-linked campus delivery milestones. Public materials do not disclose individual Q4 customer identities, contract-level value by customer, lease terms, GPU quantities by campus, data-center MW by customer, PPA or fuel-cell counterparties, rack density, network design, construction/EPC vendors, financing instrument allocations by project, or remedies if customer-delivery milestones slip.