Why it matters
The strategic read
Adds a new gigawatt-scale powered-land aggregator to the AI infrastructure map. Stark is buying a development platform built around the same bottleneck hyperscalers keep signaling: fast access to land, grid interconnection and dedicated power, with Sagebrush 1 alone described as a pathway to more than 1.5 GW of IT capacity.
Source-supported terms
What was disclosed
- 01
Stark Power announced on June 8, 2026 that it entered a definitive agreement to acquire 100% of Sagebrush Infrastructure Partners.
- 02
Stark describes Sagebrush as a developer of hyperscale data centers and co-located natural-gas-fired power plants.
- 03
The Sagebrush portfolio consists of five hyperscale data-center campuses in active development across the Central U.S.
- 04
The five-campus portfolio represents approximately 5.6 GW of aggregate IT capacity.
- 05
Sagebrush is concurrently developing co-located natural-gas-fired power plants intended to provide dedicated, reliable power delivery and reduce broader grid-constraint risk.
- 06
The portfolio is anchored by Sagebrush 1, which Stark says benefits from adjacent utility-scale power infrastructure currently under construction and has a phased path to support more than 1.5 GW of IT capacity.
- 07
Stark said Sagebrush founders Todd Cater, Timothy Dertzbaugh and Michael Whalen previously developed and monetized 4.2 GW of energy projects.
- 08
Stark recently secured approximately NIS 430M, or about $140M assuming full exercise of related securities, from Israeli institutional investors to support the Sagebrush portfolio and broader U.S. expansion.
- 09
DCD reported that Stark signed a deal to acquire the rights to the five data-center campuses and said financial terms of the acquisition were not disclosed.
Disclosure boundary
What is known—and what is not
Primary Stark Power / PRNewswire announcement plus DCD near-primary coverage. Public details disclose the buyer, seller, definitive acquisition agreement, portfolio scale, behind-the-meter gas-generation strategy, Sagebrush 1 anchor capacity and Stark financing support. Public materials do not disclose acquisition consideration, site names beyond Sagebrush 1, customer/tenant commitments, power-purchase terms, gas supply, interconnection queue positions, EPC awards, project financing, permitting status, delivery milestones or final closing conditions.