Why it matters
The strategic read
Marks Ferrovial's move from building facilities for other operators into owning and leasing digital-infrastructure capacity directly. The €1B+ program adds a major new institutional developer to Madrid's constrained data-center market, with the first 60 MW phase already through key sector reviews and cleared to begin earthworks.
Source-supported terms
What was disclosed
- 01
The Community of Madrid announced the Ferrovial Digital Infrastructure campus on July 9, 2026.
- 02
The full campus is expected to exceed 100 MW and represents more than €1B of planned investment.
- 03
The first phase is expected to deliver 60 MW.
- 04
The project has received key favorable sector reports and permission to begin earthworks.
- 05
Ferrovial previously developed Madrid data centers for Microsoft and Telefónica; this program is intended for direct leasing to customers.
Disclosure boundary
What is known—and what is not
The Community of Madrid source discloses the developer, Alcobendas location, more-than-€1B program value, greater-than-100-MW campus scale, 60 MW first phase and permitting progress. Public materials do not identify tenants, publish leases, disclose IT load, phase-level investment, site footprint, financing structure, power contracts, equipment suppliers, construction schedule, commercial terms or final delivery dates.