Meta breaks ground on C$13B Alberta AI data center

Meta Platforms + Greenlight Limited Partnership + Altalink + Capital Power + Alberta Electric System Operator

Primary sourcePress release only2026-07-08
Deal structureHyperscale AI data-center construction start / dedicated grid and generation infrastructure
GeographySturgeon County, Alberta, Canada
Infrastructure layersData centers + power infrastructure + cooling + construction / EPC
Disclosed scaleMeta says it is breaking ground on a 1 GW AI-optimized data center in Sturgeon County, Alberta, its first data center in Canada and 33rd globally, representing more than C$13B of investment once complete; Meta also says it is investing about C$60M in local road and water infrastructure and expects roughly 3,000 peak construction workers plus more than 300 operational jobs

Why it matters

The strategic read

Turns the previously unnamed Greenlight power customer into a named Meta AI-campus receipt. The scarce inputs now line up in one public trail: a 1 GW Meta-owned AI data center, fully funded generation and grid infrastructure, closed-loop liquid cooling with dry cooling, local water and road upgrades, and a separately disclosed 932 MW Greenlight gas plant with a long-term tolling structure. It is a clean example of frontier-AI demand pulling data-center capex, generation, transmission planning, water design and local infrastructure into one campus package.

Source-supported terms

What was disclosed

  1. 01

    Meta announced on July 8, 2026 that it is breaking ground on a new data center in Sturgeon County, Alberta.

  2. 02

    Meta described the project as a 1 GW data center optimized for AI workloads.

  3. 03

    The Sturgeon County facility is Meta's first data center in Canada and its 33rd data center globally.

  4. 04

    Meta said the data center will represent an investment of more than CAD $13B once complete.

  5. 05

    Meta expects approximately 3,000 construction workers onsite at peak construction.

  6. 06

    Meta expects the data center to support more than 300 operational jobs.

  7. 07

    Meta said it is investing approximately CAD $60M in local infrastructure improvements, including roads and water infrastructure.

  8. 08

    Meta said it worked with Greenlight Limited Partnership, Altalink, Capital Power and the Alberta Electric System Operator to plan for and meet the data center's energy needs years before the campus comes online.

  9. 09

    Meta said it is fully funding new generation and grid infrastructure to support the data center and that the infrastructure will improve reliability across the Alberta grid.

  10. 10

    Meta said the data center's electricity use will be matched with 100% clean and renewable energy.

  11. 11

    Meta said the Sturgeon County data center will use a water-efficient closed-loop, liquid-cooled system with dry cooling.

  12. 12

    Meta said the cooling system will have no operational water use, limiting site water use to domestic uses, fire protection safety and equipment maintenance.

  13. 13

    The Deal Room separately tracks Pembina-backed Greenlight Electricity Centre FID, a 932 MW gas-fired combined-cycle plant in Sturgeon County serving a major co-located data-center customer under a long-term electrical energy supply / tolling agreement.

  14. 14

    Pembina and Aecon primary materials described Greenlight as fully financed at C$4.6B gross project cost with Aecon's $1.7B EPC backlog share, Siemens Energy turbine package, 150 MMcf/d gas requirement and permitted expansion potential to 1,864 MW.

Disclosure boundary

What is known—and what is not

Primary Meta company announcement, linked to previously deployed primary Pembina Pipeline and Aecon / GlobeNewswire Greenlight releases. Public materials disclose Meta as the Sturgeon County data-center developer, 1 GW AI-optimized campus scale, more-than-C$13B investment amount, first-Canada / 33rd-global framing, local infrastructure investment, employment expectations, Greenlight / Altalink / Capital Power / AESO planning references, fully funded generation and grid infrastructure, renewable-energy matching, closed-loop liquid-cooling / dry-cooling design and limited operational water use. Public materials do not disclose the full energy-supply agreement, exact campus phase schedule, server or GPU counts, final building count, construction / EPC contracts for the data center itself, power price, Meta credit support, final interconnection studies, onsite substation details, cooling vendors, water-service agreements, tax incentives, delivery remedies, termination rights or the full allocation between the 1 GW data-center nameplate and 932 MW Greenlight generation capacity.