Home/Deal Room/QTS confirms $14.5B Bessemer Project Marvel campus

Data centers · Evidence brief

QTS confirms $14.5B Bessemer Project Marvel campus

QTS Data Centers + RSTL LLC + Bessemer, Alabama + Alabama Power + Warrior River Water Authority

Near-primary sourcePress release only2026-07-02
Deal structureHyperscale data-center campus land acquisition / utility and water infrastructure plan
GeographyBessemer, Jefferson County, Alabama, United States
Infrastructure layersData centers + power infrastructure + cooling + construction / EPC
Disclosed scaleQTS-linked RSTL LLC acquired roughly 1,600 acres in Bessemer for nearly $432M; AL.com describes Project Marvel as a planned $14.5B hyperscale data-center campus with 18 buildings spanning 4.5M square feet and 1,200 MW of power supplied by Alabama Power, while QTS says it is developing a Bessemer data-center facility and pursuing plans for the Project Marvel site

Why it matters

The strategic read

Adds another Blackstone-backed QTS megacampus at true AI-infrastructure scale. The scarce inputs are already bundled in the public trail: a 1,600-acre assembled site, a 1.2 GW power requirement, municipal-water agreement, closed-loop cooling claims, and a named operator with hyperscale execution across Virginia, Georgia, Texas, Ohio, Italy and Iowa. The project is politically and environmentally contested, which makes it a useful live case study for how gigawatt-class data-center campuses convert land, utility load, water commitments and community opposition into deployable infrastructure.

Source-supported terms

What was disclosed

  1. 01

    QTS lists Bessemer, Alabama as an in-development data-center campus and says it is developing a facility in the Bessemer area to support digital infrastructure used by businesses and organizations across the country.

  2. 02

    QTS says it partners with local utilities to pay 100% of its own energy use so that project-related costs are not pushed onto ratepayers.

  3. 03

    QTS says its Bessemer data centers will use a closed-loop cooling system that does not consume water for cooling once operational.

  4. 04

    WBRC reported on July 2, 2026 that a QTS Data Centers spokesperson said the company is pursuing plans for a proposed data-center campus on the Project Marvel site in Bessemer.

  5. 05

    AL.com reported on July 1, 2026, updated July 2, that QTS Data Centers bought the Project Marvel property for nearly $432M from the developer backing the project.

  6. 06

    AL.com reported the project covers roughly 1,600 acres in a rural pocket of Bessemer off Rock Mountain Lake Road / Freeman Avenue and related roads.

  7. 07

    AL.com reported that Project Marvel is planned as a $14.5B hyperscale data-center campus and has been described by city leaders as one of the largest private investments in Alabama history.

  8. 08

    AL.com reported the plan includes 18 buildings spanning 4.5M square feet.

  9. 09

    AL.com reported that Alabama Power will supply the electricity needs at 1,200 MW of power.

  10. 10

    AL.com reported that the project will use up to 130,000 gallons of municipal water per day under a new agreement with the Warrior River Water Authority.

  11. 11

    Land records cited by AL.com show the June 25 transaction moved 677 acres on Rock Mountain Lake Road for $181.6M and 932 acres on Freeman Avenue, Polara Lane and Old Lawsontown Road for $250.1M, landing with RSTL LLC, a Delaware company sharing an Overland Park, Kansas address with QTS.

  12. 12

    The project has faced local resident opposition, environmental concerns and litigation; AL.com reported the homeowner lawsuit was voluntarily dismissed the week before the July 1 story.

Disclosure boundary

What is known—and what is not

QTS primary Bessemer project page confirms the in-development campus, community engagement posture, closed-loop cooling claim and ratepayer-protection claim. WBRC confirms QTS is pursuing plans on the Project Marvel site. AL.com, citing QTS confirmation and county land records, supplies the land transaction, acreage, $432M purchase price, $14.5B planned investment, 18-building / 4.5M-square-foot scope, 1,200 MW Alabama Power requirement, municipal-water agreement and local controversy. Public materials do not disclose the full land purchase agreements, Alabama Power service agreement, power price, interconnection upgrades, final permits, data-center customer or tenant identity, phase-by-phase construction schedule, EPC awards, financing stack, cooling-equipment vendors, water-use exhibits, tax-incentive terms, lease terms, customer remedies, cancellation rights or whether the full $14.5B / 1.2 GW plan has reached final investment decision.