Why it matters
The strategic read
Pairs a large two-year AI infrastructure investment plan with long-term power procurement and grid flexibility. The capital plan covers data centers and supporting infrastructure, not a single construction contract or a disclosed amount paid to Fortum.
Source-supported terms
What was disclosed
- 01
Google announced plans to invest at least €13 billion in Finland during 2027–2028, including data centers and supporting infrastructure in Hamina, Kajaani, Muhos and Vaala.
- 02
A 22-year life-extension power purchase agreement with Fortum supports continued operation of the Loviisa nuclear power plant; a separate MoU explores additional generation and flexibility.
- 03
Additional wind PPAs bring total new-to-grid onshore wind capacity supported by Google to 629 MW; this is a portfolio total, not all newly contracted capacity.
- 04
A contracted 94 MW battery system near Kajaani is expected to connect to the grid in late 2027.
Disclosure boundary
What is known—and what is not
Issuer-announced investment plan, not completed expenditure. Campus MW, individual EPC awards, annual spending, construction conditions and PPA pricing are not disclosed. New nuclear cooperation is an MoU rather than a reactor order.